Those three categories alone account for roughly 88% of the starting capacity. Moratoriums typically freeze new applications rather than revoke existing approvals. And even when a restriction applies, equipment lead times, litigation or other constraints may already determine the delivery date. A pause adds delay only if it pushes the project beyond that timeline. (4/5)