SemiAnalysis 在二季度数据中心产业走访中发现,模块化产能已售罄,需求增速超过产能爬坡速度。模块化因同时缓解工期与现场劳动力两大制约而提升份额,电力与冷却系统可在工厂组装、外壳在现场同步搭建,交付周期最多压缩 40%,部分建设环节的现场工时最多减少约 70%。相关内容在其近期 newsletter 中拆解了不同方案及工期、人力与成本节省。
Another theme that emerged from our Q2 tour of datacenter industrials is that modular capacity is sold out, with demand growing faster than the pace of capacity bring-up. Modular is gaining share because it addresses the two biggest constraints on datacenter construction: time and field labor. Power and cooling systems can be assembled in factories while the shell goes up on site, compressing delivery timelines by up to 40% and reducing on-site man-hours by up to ~70% for some parts of the build. We broke down the different approaches—and the schedule, labor and cost savings—in our recent newsletter (1/4)🧵 https://t.co/7I01B8Udo9
来源:@SemiAnalysis_ · x.com