SemiAnalysis 根据文件指出,这座 8 GW 数据中心园区至少横跨三块地块,各自的开发路径并不相同。
从土地权属与审批文件看,园区被拆成三条开发路径,读者可据此判断各阶段的落地节奏。
But the filings tell a broader story. The 8 GW campus appears to span at least three distinct land positions, each with a different development path.
🟠 The DOE site. This is the parcel at the center of the headlines. It remains subject to a federal cleanup program running through 2031, with site preparation still awaiting regulatory sign-off.
🟠 2,700 acres of private farmland. Located north and east of the old plant, this land is central to SB Energy’s initial development plans. Its May Ohio permitting filing outlines a first phase with two buildings. However, SB Energy only holds options on the land, and a wetlands permit is not expected until the end of 2026.
🟠 A third, previously unannounced parcel. On the day the deal became public, county records show SB Energy taking ownership of a former DOE parcel that has already been environmentally released, with no demolition pending. (2/5)
来源:@SemiAnalysis_ · x.com